Project Background
Our client RINGWAY, requested to upgrade the Gents Toilet Facilities, to include new cubicles, toilets, vanity units, hand driers and heating.
![](http://13.41.182.173/wp-content/uploads/2019/04/IMG_5318-770x650.jpg)
![](http://13.41.182.173/wp-content/uploads/2019/04/IMG_5323-770x650.jpg)
![](http://13.41.182.173/wp-content/uploads/2019/04/IMG_3686-770x650.jpg)
Our Solution to deliver the works
To supply all necessary labour and materials to refurbish the gent’s toilet to include the following works:
• To attend site and strip out the old toilet cubicles and urinals all back to the timber carcasses
• Isolate all water services
• Remove the 3 sinks and vanity top and panels leaving the carcasses.
• Remove 2 hand dryers and wall shelving
• Supply labour to install new IPS panels on the existing carcasses.
• Fit new vanity top and panels with centre storage,
• Fit 3 new cubicles and concealed back panelling to toilet area complete with soft close seats to the pans, coat hooks on the rear of the doors and toilet roller holders.
• Fit new panels and privacy panels to the urinal area, waterless urinal to be re used with new cartridges installed.
• Apply bio glad panel to the wall where the tiles altered for re location of the hand dryers.
• Supply and fit and re-configure plumbing to accommodate a new radiator.
Project Outcome:
This project is now complete, the client is extremely happy with the works and has assured us that we will be involved with any future upgrade works on other sites.