Project Background
We were requested to carry out an investigation as to the reasons for the existing Pump Station failing on a regular basis causing disruption to the site. Upon investigation it was found that the existing system had failed due to lack of maintenance and poor installation.
![](http://13.41.182.173/wp-content/uploads/2019/05/IMG_0652-770x650.jpg)
![](http://13.41.182.173/wp-content/uploads/2019/05/IMG_0646-770x650.jpg)
![](http://13.41.182.173/wp-content/uploads/2019/05/IMG_1321-770x650.jpg)
Our Solution to deliver the works
To supply and install new Package Pump Station to include the following works:
• Saw cut, break out & excavate a hole for new PPS approximately 4.3mtrs deep.
• Supply & install a new concrete base ready to receive the new chamber.
• Install package pump system
• Supply and install required drainage alterations from the existing chamber.
• Supply and install concrete surround to chamber and pipework.
• Backfill and consolidate holes/ trenches
• Make good to surface as existing.
• Pump out and backfill existing chamber with concrete
• Disposal of all spoil arising
• Connection from rising main to new pumping station
Providing Solutions From Start To finish
This project is now complete, we have also implemented a 6 monthly maintenance schedule to clean and inspect the package pump system to ensure that the system is fully maintained for future use.